Padma Bridge At a Glance
Padma bridge at a glance. Today we will give a overview about Padma Bridge. Padma Bridge is a very important topic for job exam. The Padma Bridge is a multipurpose road-rail bridge across the Padma River to be constructed in Bangladesh. It will connectLouhajong, Munshiganj to Shariatpur and Madaripur, linking the south-west of the country, to northern and eastern regions. Padma Bridge is the most challenging construction project in the history of Bangladesh. The two-level steel truss bridge will carry a four-lane highway on the upper level and a single track railway on a lower level. With 150 m span, 6150 m total length and 18.10 m width it is going to be the largest bridge in the Ganges-Brahmaputra-Meghna river basins of country in terms of both span and the total length.

Loading...

Component Of the Padma Bridge Project:

Main Bridge
River Training Works(RTW)
Janjira Approach Road & Selected Bridge End Facilities
Mawa Approach Road & Selected Bridge End Facilities
Service Area-2
Resettlement
Environment
Land Acquisition
CSC(Main Bridge & RTW)
CSC(Approach Roads & Service Area-2)
Engineering Support & Safety Team(ESST)
Main Bridge (6.15 km long): Contractor: China Major Bridge Engineering Co. Ltd, China. Contract Period : 4 years+1year (defect liability period). Contract Cost : BDT: 12,133.39 crore. Date of work order: 26 November 2014. Date of Completion . Physical Progress of Work: Mobilization of equipment & procurement of materials, as well as preparatory works such as geotechnical investigation, survey, steel fabrication of test pile, dredging and Contractor’s accommodation, stack yard, casting yard etc. construction, are going on.


River Training Works(14 km length): Contractor : Sinohydro Corporation Limited, China. Contract Period : 4 years+1year (defect liability period). Contract Cost : BDT: 8707.81 crore. Date of work order : 31 December 2014. Date of Completion : . Physical Progress of Work : Handed over land to Contractor, Mobilization of equipments & procurement of materials as well as Contractor’s accommodation, stack yard, casting yard etc. construction are going on.

Janjira Approach Road & Selected Bridge End Facilities (10.5 km length): Contractor : AML-HCM JV. Contract Period : 3 years+1year (defect liability period). Contract Cost : BDT: 1097.40 crore. Date of work order : 8 October 2013. Physical Progress of Work : 29.10%.
Mawa Approach Road & Selected Bridge End Facilities (1.5 km length): Contractor : AML-HCM JV. Contract Period : 2.5 years+1year (defect liability period). Contract Cost : BDT: 193.40 crore. Date of work order : 27 January 2014 Physical Progress of Work : 21.5%.

Service Area-2: Contractor : Abdul Monem Ltd. Contract Period : 2.5 years+1year (defect liability period). Contract Cost : BDT: 208.71 crore. Date of work order : 12 January 2014 Physical Progress of Work : 12%.
Resettlement: Total Additional Grant Paid to the PAP : BDT: 500.71 crore(up to 31 December 2014). Total no. of plots : 2698 No. of residential plots : 2618 No. of commercial plots : 80 977 plots have been handed over to the PAP out of approved 1045 plots(up to 31/12/2014).

Environment: Tree plantation has been started from 2012 and 55150 nos. of tree plantation has been completed up to-date.

Land Acquisition: Land has been acquired 1408.54 hectre.

CSC (Main Bridge & RTW): Consultant : Korea Expressway Corporation, South Korea & Associates. Contract Period : 4 years+1year (defect liability period). Contract Cost : BDT: 383.15 crore. Date of Signing Contract : 3 November 2014. Progress of Work : Deployment of manpower as well as supervision of works are going on.

CSC (Approach Road & Service Area): Consultant : Special Works Organization(SWO-West), Bangladesh Army in association with BRTC, Bangladesh University of Engineering and Technology. Contract Period : 3 years+1year (defect liability period). Contract Cost : BDT: 133.49 crore. Date of Work Order : 13 October 2013. Progress of Work : 40%.

Engineering Support & Safety Team(ESST): ESST : Bangladesh Army. Contract Period : 4 years+1year (defect liability period). Contract Cost : BDT: 72.14 crore. Date of Work Order : 13 October 2013 Progress of Work : 40%